implementation |
||
![]() |
![]() |
![]() |
Inside the concrete tank before insulation |
first operation : insulation, the insulation panels are pasted on the walls (6 sides) |
the tank is now insulated on 6 sides |
![]() |
![]() |
![]() |
second operation : fixing the spraying pipes on the ceiling |
third operation : fitting the prefabricated liner. The liner is unrolled on a safeguard carpet on the ground |
the liner is fastened on the upper part of the walls |
![]() |
![]() |
![]() |
waterproof crossing of the liner and fixing the strainer |
fourth operation : water test : the tank is filled with water |
Fifth operation : filling the thank with Ice Containers |
![]() |
![]() |
|
the tank filled with Ice Containers is now ready to operate |
sixth operation :spraying tests before starting. |
|